Blog›EVM Formulas: CPI, SPI, EAC, and ETC Step by Step
EVM

EVM Formulas: CPI, SPI, EAC, and ETC Step by Step

July 30, 2026 · 10 min read · 📐

Project Example: Road Construction

BAC

$500,000

Total budget

PV

$140,000

Planned to date

EV

$120,000

Work done (budget)

AC

$130,000

Real spend to date

All 8 EVM Formulas

CPI = EV / AC

Cost efficiency index

0.92

Over budget

SPI = EV / PV

Schedule efficiency index

0.86

Behind schedule

CV = EV − AC

Cost variance

-$10,000

Negative (over)

SV = EV − PV

Schedule variance

-$20,000

Negative (behind)

EAC = BAC / CPI

Estimated cost at completion

$541,667

Over budget

ETC = EAC − AC

Remaining cost to complete

$411,667

Remaining spend

VAC = BAC − EAC

Final cost variance

-$41,667

Overrun expected

TCPI = (BAC−EV)/(BAC−AC)

Required future efficiency

1.03

Challenging

Summary Table

IndicatorFormulaResultStatus
CPIEV / AC0.92🔴
SPIEV / PV0.86🔴
CVEV − AC-$10,000🔴
SVEV − PV-$20,000🔴
EACBAC / CPI$541,667🔴
ETCEAC − AC$411,667🟢
VACBAC − EAC-$41,667🔴
TCPI(BAC−EV)/(BAC−AC)1.03🟢

Calculate all 8 EVM formulas automatically