Plan and control power generation, transmission, renewable energy and oil & gas projects with high-precision schedules and EVM control.

Start free→View plans

No credit card · Free · 1 active project

The problem

What makes energy project management hard

!

Contractual milestones with delay penalties

In energy projects, delays carry daily penalty clauses. TPLANNER's critical path analysis and SPI alerts identify at-risk milestones weeks in advance.

!

Coordination across engineering, procurement and construction

EPC projects run three simultaneous fronts. TPLANNER lets you view the integrated schedule with cross-discipline dependencies and critical path alerts.

!

Reports for lenders and regulatory bodies

Energy projects report to banks, investors and regulators. TPLANNER's executive reports with S-curve and EVM meet the formats expected by international lenders.

The solution

TPLANNER for energy

Integrated EPC schedule

Manage Engineering, Procurement and Construction phases in a single Gantt. Cross-discipline dependencies and automatic critical path alerts.

Critical milestone traffic lights

Define contractual milestones and receive alerts when the associated package SPI falls below the threshold. Anticipate delays before they happen.

S-Curve and physical progress

Record physical progress by specialty and visualise the cumulative S-curve. Ideal for lender reports and payment milestone closures.

Reports for lenders

Export executive reports with S-curve, EVM table, status by discipline and executive narrative. Clean format for banks, investment funds and regulators.

Use cases

How energy teams use TPLANNER

Case 1

50 MWp solar park · Ica, Peru

$38M project, 14 months. Procurement and construction controlled in parallel. Early SPI 0.82 alert in week 10 due to delayed imported equipment.

Outcome

Construction sequence reorganised. Commercial operation on schedule.

Case 2

Transmission substation · Colombia

$12M project with contractual energisation milestone. CPI of 0.93 detected in month 5 allowed renegotiation with the electromechanical contractor before the critical milestone.

Outcome

Milestone closed on time. No penalty clause triggered.

Start today

Your next energy project
under control from day 1

Free Starter plan · 1 active project · No credit card

Create free account →📊 Free EVM Calculator

Frequently asked questions

Does TPLANNER handle multi-currency projects?

Currently costs are entered in one currency per project (user-defined). Multi-currency support is on the roadmap.

Can I generate the S-curve for lender reports?

Yes. The cumulative S-curve (planned vs. actual) is generated automatically and can be exported as part of the executive report in PDF.

Does the system have read-only access for auditors?

The Enterprise plan includes collaborator access. Read-only permissions for external auditors are on the roadmap.

Also available for

🏗️ Construction⛏️ Mining🏭 Manufacturing🌉 Infrastructure💧 Sanitation

¿Quieres recibir nuevos artículos?

Escribimos sobre lo que realmente importa en la gestión de proyectos industriales.

Sin spam. Cancela cuando quieras.